·
26.04.2012
·
25.04.2012 Notice of special information about the issuer
·
07.03.2012 For the attention of shareholders PJSC "SVS-Dnipro"
  last news

·
01.10.2010 Laying of high-voltage CL in Ukraine - the experience of "SVS-DNIPRO" company. Elektropanorama # 9, 2010.
·
16.06.2010 Vladimir Vypyraylo: motto of "SVS-DNIPRO" – always be on step ahead of!
·
16.06.2010 "SVS-Dnepr": advanced experience of installation the unique KRUE 330 kV of Dnestrovskaya PSP

Name
E-mail

GISMETEO: Погода по г.Киев
Publication

Present-day high-voltage CL: installation and maintenance experience. Part 3

Second part of the article

Table 7. Damage ratios of cable lines with elements distribution in correlation to the amount of damages for 100 km. All registered damages (1).

 
 
Line’s component
Lines with XLPE (kV) insulation
Lines with paper-oil insulation (kV)
60-219
220-500
Total
60-219
220-500
Total
Cable
0,085
0,133
0,088
0,109
0,248
0,149
Connection box
0,007
0,048
0,004
0,0065
0,014
0,006
Terminal box
0,011
0,050
0,013
0,014
0,028
0,019
 

Besides, the time for damages removal was also analyzed. Different conditions had been examined.  

For instance, for the cable lines of ac voltage from 60 up to 219 kV in other words the most interesting segment of voltages for the power engineering specialists, up to 90% of damages had been removed during the period up to one month, but 5% of damages for the cable in paper-oil insulation the period of damages removal was more than three months. Comparison of time for damages removal in the cable lines with extruded insulation and cables with paper-oil insulation for the whole spectrum of voltages are represented on drawing 3. The time of damages removal in the ac voltage cable lines is shown in table 8 and on drawing. An average time of repair for the cable lines with XLPE insulation makes 20 days, but for the cable lines with low pressure paper-oil insulation - 29 days.

 
 
120 
 
 
 
100
 
 
 
 Row 1
80
 
 
Row 2
 

Row 3  

60
 
 
 
Row 4
 
40
 
 
 
 
20
 
0
 
 
 
 

Insulation made of artificial plastic                                       Paper insulation                

Row 1 - less than 1 week

Row 2 - from 1 week up to 1 month

Row 3 - 3 months

Row 4 - more than 3 months





 

Drawing 3 - Percent distribution of time duration for repair the cable lines laid overland with paper insulation and insulation made of artificial plastic.

Table 8. Average time of repair in days for different design of the cable for high and extra-high  voltage.
 
Voltage level (kV)
Cable design

Paper insulation  + oil

internal pressure

Extruded insulation

(elastrons)
From 60 up to 219
20
15
From 220 up to 500
38
25
 

At analysis of the cable lines damage cases we examined only the time of repair, for the cases when this period was not less than 1 day and no more than 6 months. The cases outside of these time limits were not taken into account. For the cable lines with voltage up to 220 kV the difference of average time for repair is equal to 5 days for two the most popular designs, used today for cabling into soil. But in case of higher voltage it requires longer period of time, and difference is already equal to 14 days. The time for damages elimination in the analyzed cable lines is equal to from 1 day up to 6 months. Anaverage time, expressed in the amount of days required for repairing of cable lines laid overland, by two most often used methods of cabling is shown in table 9. For the voltages up to 210 kV practically there are no differences, but at higher voltages this time period in average is for 20 days more at cabling in channels, underpasses, piped passages. But here we can dispute grouping of such cable damages cases at cabling in piped passages and underpasses.

 
Table 9. Average time in days depending on methods of cabling.
 
Voltage level (kV)
Laying of cable line
Directly into ground
Pipes, channels, underpass
from 60 up to 219
14
15
from 220 up to 500
25
45
 

Comparison of data regarding accident rate of cable lines collected from different documents is represented in table 10. Received data seems too optimistic, since following years include greater number of lines in the network.

Table 10. Comparison of data regarding accident rate of cable lines for the period since 1991 up to 2008 (1).
Publication
CIGRE article
 2-07    1991
CIGRE article
2-07    1991
CIGRE WG
B1-10    2008

Period of analysis

1950-1980
1980-1990
1990-2005

Length of cable lines

3 610
no data
7 100

Number of damages

154
116
49

Damage ratio

0,32
no data
0,12

Average time of line disconnection

37
70
60
 
Conclusion

The development of cable lines is an accomplished fact. We are observing dynamic increase of the amount of cable lines which are under construction, not only due to the need of increasing the amount of delivered electric power to greater number of the users, but also as the achievement of results on assurance of reduction the influence of energy facilities on environment.

Literature (1)    Rosevear R.D., Choquette, Fairhurst M., Jorgensen H.J., Larsen J.E., Mampeay B., Rakowska A., Tricoli S., Waschk V. Update of service experience of HV underground and submarine cable systems, CIGRE TB 379, April 2009, ISBN 978-2-85873-066-7, s. 1-84.

(2)   Swingler S., Barber K., Daly J., Award R., Antic J., Zenger W. Statistics of AC underground cables in power networks, CIGRE TB 338, WG B1-07, December 2007.

(3)   Rosevear R.D., Choquette, Fairhurst M., Jorgensen H.J., Larsen J.E., Mampeay B., Rakowska A., Tricoli S., Waschk V. Update of service experience of HV underground and submarine cable systems, ELECTRA, No 245, April 2009, CIGRE, pp. 53-57.

(4)   Kobayashi S., Tanak S., Suetsugu M. Development of factory-expanded cold-shrinkable joint EHV XLPE cables, JICABLE 2003, paper A5.1




« назад
Dnestr photo
110/35/6 SS of Volyntsement OJSC, Zdolbuniv, Rivne region

Headquarters:
4a, Promyshlennay St., Kiev, 01013
Phone: +38 (044) 545-71-24, 25
Production facilities:
4, Shkolnaya St., Vyshgorod, 07300
Phone: +38 (044) 430-36-17, 451-67-21,
+38 (04496) 54-9-23
 
© 1993 - 2011 SVS-Dnepr PJSC . All rights reserved.