His conscious life in the whole is dedicated to the construction of power facilities. More then 20 years experience of construction and electrical mounting works on different projects - from the nuclear power plants up to low voltage systems of power supply are behind his shoulders. He has enough what to tell.
V.V.CJSC "SVS-Dnipro" is in stable operation, and fulfill all contract obligations. The personnel are provided with a scope of works. I suppose that taking into account general economic situation of the present-day we can consider these results as satisfactory, and even good. I can't say that we do not have the problems, but we evaluate them adequately and make the decision by the joint efforts.
How did you become the Director of one of the largest electrical installation enterprise in Ukraine?
V.V. According to my education - I am electrical-engineer. After service in army, in 1986 I graduated from the Kiev Polytechnic Institute (the faculty of electrical engineering, chair of "Power plants"). According to the distribution I was hired to the All-Union of Red Banner order "Gidroelektromontazh" trust. I had participated in the damages liquidations on CNPP (Chernobyl Nuclear Power Plant), worked at the starting unit of Khmelnitsky NPP, on Kurskaya NPP, took part in reconstruction works after earthquake in Armenia (Leninakan city). Then I worked at NPP Huragua (Cuba). We had been mounting the reactor VVER 440. Unfortunately we didn’t finish the construction – the USSR has collapsed. At the beginning of 90-th years I have returned to Kiev. Entirely other times have come. "SVS-Dnipro" has been organized in 1993.
● mounting of overhead and cable lines of 0,4 - 110 kV;
● construction of switchgears of 0,4 - 330 kV;
● laying of the engineering networks, including heat supply mains and cable-and- trumpet
● construction of industrial and domestic installations.
voltages 35-110-220-330 kV. In the centre – we are mounting closed SS 110/10 KV "Zdolbunov". Well, and of course the projects in Kiev.
V.V. At present, reliable power supply in the capital of the Ukraine is the enormous problem. At present, reliable power supply in the capital of the Ukraine is the enormous problem. It was not formed today and even not yesterday, and is the result of allreasons that are stated above. Today’s attempts of JSC "Kievenergo" to solve the strategic problems of the city’s power supply system development are connected with stupendous problems of administrative nature. In particular, the question of the sites allotment for the construction of electrical power projects is considered today
as an equal with construction, for instance, an ordinary shopping center that absolutely is not correct.And by the way, it is not a fact that vitally important for city the territory for construction of the new substation or laying of the cable line will be admeasured exactly for this, rather then for the new trade or office centre. Sometimes I am thinking – is it really has to occur (God forbid!) the serious accident with "blackout" the most of the city (as it was, for instance, in Moscow) that, at last, all officials of the city came to united understanding of vital necessity to make consolidated strategic decision.
Does the "SVS-Dnipro" as erection organization feel these problems?
But if the project is constructed for budgetary funds?
V.V. In this case the order of action is clearly prescribed - first competitive bidding for the fulfillment of design work (at that, the procedure of the undertaking the competitive bidding on designing for budgetary and equated to them funds provides step-by-step designing). From the very beginning design institute shall define the main parameters of the project WITHOUT CONNECTION IT to the equipment or supplying factories. And herewith only good intentions are pursued in order to prevent lobby of anyone's interests. And thereafter - the following stage – the competitive bidding on buying the equipment is declared. And only on the third stage this equipment is adapted to already performed project. It looks like everything is logical. But in practice we have a terrible situation of maximum time delay for the designing and, as a result, lowering the quality of project.
V.V. We diversify our activity for optimization of the process controllability. We have created several affiliated enterprises, which are assigned to certain types of activity: installation of electrical equipment, cable facilities, systems of the automation, adjustment subdivisions, enterprise, that is specialized in execution of works with the use of machinery that is related to a significant transportation of soil including transportation in city condition.
In due time we created the separate construction section that was responsible for the fulfillment of construction works at the project - walls, roof covering etc. At the increase the scope of works this section turned into self-independent construction enterprise – finishing works, sanitary engineering section etc. In other words today we are able to perform the whole complex of civil and erection works - from foundation up to finishing works. And the completion stage - preparation the whole complex of specific regulation documents for the power installations. These are complex and labor-consuming, but absolutely necessary documents, without which it is impossible to put the power installation into operation.
The System of quality assurance in accordance with requirements of the international standard ISO 9001:2000 was developed and introduced in CJSC "SVS-Dnipro" since 2002.In 2007 the system successfully passed through the certificate audit that was carried out by "TYUF-NORD Ukraine" the international agency on certification. The expansion of the enterprise activity sphere has caused the necessity of spreading the activity of system quality on all subsidiary production enterprises of the company.
The managers and specialists of the enterprise are constantly improving their professional skills, they are getting training by the programs of the International Institute on Projects Management (PMI). Moreover, the employees of CJSC "SVS-Dnipro" are constantly attending the profiled exhibitions, get acquainted with the new engineering decisions. This is much helping in their activity.
V.V. With pleasure. Due to acute lack of free areas in the densely populated part of Kiev the specialists of CJSC "SVS-Dnipro" have successfully mastered innovation technology of designing and construction of underground and partially recessed substations and TSS. Our specialists more than once visited the Czech Republic, and adopted the leading experience. And now we can be proud of our experience of construction these complex engineering structures.
V.V. Usually we have in production up to fifty agreements simultaneously and, accordingly, the same number of projects. In other words, we are working in multi-project mode. I can tell you with confidence: in 2008, as by the way in earlier too, we do not have none of fouled-up project. And I am proud of this. All projects of this year are not simple, especially city’s projects. In particular, to the most significant we can refer the reconstruction of SS 110 kV "Solomenskaya" and "Vokzalinaya". These projects are rather complicated from the technological point of view. Specific character of activity on substations, which are practically in operation during the whole year in the mode of loading close to maximum parameters, requires extremely coordinated functioning with operating personnel of the "Cable networks" branch of JSC "Kievenergo", and occasionally - non-standard decisions. On reconstruction of SS "Vokzalinaya" the cable ring of 110 kV from SS "Bastionnaya" to SS "Octyaberskaya" through the SS "Centre", "Vokzalinaya", "ST1" and "Polytechnicheskaya" was closed. This has allowed improving in considerable extent the reliability of power supply to the right-bank part of Kiev city.
Your forecasts and wishes for 2009
In 2009 it would be desirable to have intelligible policy and integrated solutions on way out from crisis. Today the personnel of CJSC "SVS-Dnipro" are a united team of professionals, which are able to solve the utmost difficult problems. We have high-skilled nice young people and experienced specialists, who have been working in power field fore many years. Our main priority is expediency and common sense to the benefit of business. And always be on step ahead.